A picture containing logo

Description automatically generated 

Graphical user interface, text, application

Description automatically generated

Text

Description automatically generated

 

 

 

 

  

Contents

Executive summary

1       Introduction

1.1      Background

1.2      Scope of this Report

1.3      Organisation Structure

1.4      Summary of Construction Works

1.5      Summary of EM&A Requirements

1.6      Status of Statutory Environmental Compliance with the Environmental Permit

1.7      Status of Other Statutory Environmental Requirements

1.8      Reporting of EM&A Results

2       Air Quality

3       Noise

3.1      Monitoring Requirements

3.2      Monitoring Locations

3.3      Monitoring Parameters, Frequency, Duration and Monitoring Dates

3.4      Action and Limit Levels

3.5      Monitoring Equipment

3.6      Monitoring Schedule for the Reporting Period

3.7      Results and Observations

4       Water Quality

5       Ecology

6       Waste Management Status

6.1      General

7       EM&A Site Inspection

7.1      Monitoring Requirements

7.2      Site Inspections and Key Observations

8       Implementation Status of Environmental Mitigation Measures

9       Summary of Exceedances of the Environmental Quality Performance Limit

10     Summary of Complaints, Notification of Summons and Successful Prosecutions

11     Future Key Issues

11.1     Construction Programme for the Coming Reporting Period

11.2     Monitoring Schedule for the Coming Reporting Period

12     Conclusions and Recommendations

Figures

Appendices

A.      Project Organisation

B.      Construction Works Programme

C.      Environmental Mitigation Implementation Schedule

D.      Status of Submissions and Implementation Status of Mitigation Measures under EP

E.      Status of Statutory Environmental Requirements

F.      Noise

G.      Cumulative Statistics on Exceedances, Environmental Complaints, Notifications of Summons and Status of Prosecutions

H.      Monitoring Schedule for the Next Reporting Period

 

Tables

Table 1.1: Commencement Dates of Construction Works for the Active Works Contracts  3

Table 1.2: Contact Information of Key Personnel 4

Table 1.3: Major Activities in the Reporting Period  5

Table 1.4: Summary of Status for the Environmental Aspects under the Updated EM&A Manual 6

Table 3.1: Impact Construction Noise Monitoring Stations  10

Table 3.2: Impact Construction Noise Monitoring Parameters, Frequency, Duration and Monitoring Dates  10

Table 3.3: Action and Limit Levels for Construction Noise  11

Table 3.4: Noise Monitoring Equipment 11

Table 3.5: Summary of Construction Noise Monitoring Results in the Reporting Period  11

Table 6.1: Quantities of Different Waste Generated and Imported Fill Materials  15

Table 7.1: Key Observations Identified during Site Inspections in this Reporting Period  17

Table 11.1: Major Activities for the next Reporting Period  22

 

 

 

 

 

 

Executive summary

Tung Chung New Town Extension (TCNTE) is one of the major initiatives under the Government's multi-pronged approach to increase land supply to meet Hong Kong's medium- to long-term needs for housing, economic and social developments. The Environmental Impact Assessment (EIA) Report for TCNTE (Register No. AEIAR-196/2016) was approved on 8 April 2016 and the Environmental Permit (EP) No. EP-519/2016, covering the construction and operation of TCNTE, was granted on 9 August 2016. The EIA Report and EP cover both Tung Chung East (TCE) and Tung Chung West (TCW) (hereafter referred to as "the Project").

Civil Engineering and Development Department (CEDD) commissioned Mott MacDonald Hong Kong Limited (MMHK) to undertake the role of Environmental Team (ET) for carrying out the Environmental Monitoring & Audit (EM&A) works during the construction phase of the Project in accordance with the requirements specified in the EP, Updated EM&A Manual (the Manual), EIA Report of the Project – i.e., Tung Chung New Town Extension (TCNTE) development in Tung Chung West (TCW) and other relevant statutory requirements.

This EM&A Report summarises the monitoring results and audit findings of the EM&A programme undertaken for the TCW Project during the reporting period from 3 to 30 November 2021 in accordance with the Manual. A summary of the monitoring and audit activities conducted in the reporting period is listed as below.

Summary of Monitoring and Audit Activities in the Reporting Period

Parameter

Number of Sessions

Air Quality Monitoring

0 sessions

Noise Monitoring

4 sessions

Water Quality Monitoring

0 sessions

Environmental Site Inspection

Contract 5: 5 sessions

Contract 6: 0 sessions

Environmental auditing works, including weekly site inspections of construction works conducted by the ET, audit of implementation of Habitat Enhancement and Translocation Plan for Amphibian Species of Conservation Importance and Waste Management Plan were conducted in the reporting period. Based on the audit results and the observation for the reporting period, environmental pollution control and mitigation measures for the Project were properly implemented.

 

Breaches of Action and Limit Levels for Air Quality

No impact air quality monitoring was scheduled during the reporting period.

 

Breaches of Action and Limit Levels for Noise

Impact noise monitoring at the village house in Ma Wan Chung (NMS-CA-5) was carried out.  No exceedance of Action and Limit Levels was recorded for construction noise monitoring in the reporting period.

 

Breaches of Action and Limit Levels for Water Quality

No impact water quality monitoring was scheduled during the reporting period.

 

Ecological Monitoring

No impact ecological monitoring was scheduled during the reporting period.

 

Environmental Complaints, Non-compliance & Summons

There was no environmental complaint, notification of summons or prosecution recorded in the reporting period.

 

Reporting Change

There was no reporting change in the reporting period.

 

Summary of Upcoming Key Issues

Contract No. NL/2020/05 ("Contract 5") - Ma Wan Chung

● Ground Investigation;

● Geotechnical Investigation;

● Site Survey.

 

Contract No. NL/2020/06 ("Contract 6") - Tung Chung Valley

● Site Clearance;

● Fence Wall Construction.

 

 

1        Introduction

1.1        Background

 

Tung Chung New Town Extension (TCNTE) is one of the major initiatives under the Government's multi-pronged approach to increase land supply to meet Hong Kong's medium- to long-term needs for housing, economic and social developments. The Environmental Impact Assessment (EIA) Report for TCNTE (Register No. AEIAR-196/2016) was approved on 8 April 2016 and the Environmental Permit (EP) No. EP-519/2016, covering the construction and operation of TCNTE, was granted on 9 August 2016. The EIA Report and EP cover both Tung Chung East (TCE) and Tung Chung West (TCW) (hereafter referred to as "the Project").

Civil Engineering and Development Department (CEDD) commissioned Mott MacDonald Hong Kong Limited (MMHK) to undertake the role of Environmental Team (ET) for carrying out the Environmental Monitoring & Audit (EM&A) works during the construction phase of the Project in accordance with the requirements specified in the EP, Updated EM&A Manual (the Manual), EIA Report of the TCW Project and other relevant statutory requirements. The scope of the Project works in TCW includes the following elements:

·         Site formation works;

·         Construction or the River Park including a visitor centre;

·         Construction of proposed open space;

·         Construction of sustainable urban drainage system;

·         Construction of roads, footpath and the associated junction / road improvement works;

·         Construction of coastal pedestrian access;

·         Engineering infrastructure works covering drainage, sewerage, waterworks and landscaping works; and

·         Implementation of environmental mitigation measures and environmental monitoring and audit works.

The construction works for the Project were commenced on 3 November 2021 and are divided into various works contracts. The following active works contracts were commenced on the dates shown in Table 1.1.

Table 1.1: Commencement Dates of Construction Works for the Active Works Contracts

Contract No.

Contract Name

Commencement Date of Construction Works

Contract No. NL/2020/05 ("Contract 5")

Tung Chung New Town Extension – Site Formation and Infrastructure Works at Ma Wan Chung

3 Nov 2021

Contract No. NL/2020/06 ("Contract 6")

Tung Chung New Town Extension – Site Formation and Infrastructure Works at Tung Chung Valley, Phase 1

3 Nov 2021

(Note: Construction works at Tung Chung Valley commenced on 30 Nov 2021)

The locations of Contracts 5 and 6 are shown in Figures 1.1 and 1.2 respectively.

1.2        Scope of this Report

This is the Monthly EM&A Report for the TCW Project which summarises the key findings of the EM&A programme for the construction works during the reporting period from 3 to 30 November 2021.

1.3        Organisation Structure

The organisation structure of the Project is shown in Appendix A. The key personnel contact names and contact details of the active works contracts are summarized in Table 1.2 below.

Table 1.2: Contact Information of Key Personnel

Party

Position

Name

Telephone

Contract No. NL/2020/05 ("Contract 5")

Tung Chung New Town Extension – Site Formation and Infrastructure Works at Ma Wan Chung

Project Proponent

(Civil Engineering and Development Department (CEDD))

Chief Engineer

Gavin Wong

2231 4439

Senior Engineer

Gary Yung

2195 0847

Engineer

Carol Lam

2231 4472

Engineer’s Representative (ER)

(Ove Arup and Partners Hong Kong Limited)

Principal Resident Engineer

Jackson Wong

5699 5710

Resident Engineer

Sam Chan

9671 5538

Senior Inspector of Works

Tony Chiu

5699 5792

Contractor

(Build King – Richwell Civil Joint Venture)

Project Manager

Eric Yip

9196 6098

Construction Manager

Artie Wong

9633 0977

 

Site Agent

Ricky Hon

9100 7509

 

Environmental Officer

Calvin Chan

6117 2894

 

24-hour Complaint Hotline

-

9326 1161

Contract No. NL/2020/06 ("Contract 6")

Tung Chung New Town Extension – Site Formation and Infrastructure Works at Tung Chung Valley, Phase 1

Project Proponent

(Civil Engineering and Development Department (CEDD))

Chief Engineer

Gavin Wong

2231 4439

Senior Engineer

CT Lam

2231 4469

Engineer

Samuel Yiu

2231 4510

Engineer’s Representative (ER)

(Ove Arup and Partners Hong Kong Limited)

Principal Resident Engineer

Jackson Wong

5699 5710

Resident Engineer

Shirley Yeung

9671 5518

Senior Inspector of Works

Jensen Lo

5699 5746

Contractor

(China Railway Group Limited)

Project Manager

Gregory Lo

9333 5171

Deputy Project Manager

Yang Wei Cai, Yancy

6218 6768

Deputy Project Manager / Superintendent

Robert Luo

9588 2485

 

Construction Manager

Paul Chan

6263 0621

 

Environmental Officer

Simon Mak

5560 8600

 

24-hour Complaint Hotline

-

9326 1161

Environmental Team (ET)

(Mott MacDonald Hong Kong Limited)

ET Leader

Daniel Sum

2585 8495

 

Deputy ET Leader

Heidi Yu

2828 5704

Independent Environmental Checker (IEC)

(Binnies Hong Kong Limited)

IEC

Manuel Chua

3894 9501

 

Deputy IEC

Edward Lau

3894 9502

1.4        Summary of Construction Works

The programme of the construction is shown in Appendix B.

As informed by the Contractors of the active works contracts, details of the major works carried out in this reporting period are listed in Table 1.3.

The environmental mitigation implementation schedule is presented in Appendix C.


 Table 1.3: Major Activities in the Reporting Period

Activities

Key Issues

Key Mitigation Measures

Contract No. NL/2020/05 ("Contract 5")

Tung Chung New Town Extension – Site Formation and Infrastructure Works at Ma Wan Chung

         Ground Investigation Works

         Initial Survey

         Site Clearance

         Dust Emission

         Handling and storage of C&D materials generated from construction activities

         Noise from plant operation

         Emission of dark smoke from PMEs

         Tree Protection

         Good site practices

         Regular water spraying on stockpiles

         Provide tarpaulin sheets coverage on stockpiles

         Sorting and reuse of C&D materials as far as practicable

         Use of QPME and noise barrier/acoustic mat

         Regular maintenance of PMEs

         Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works

Contract No. NL/2020/06 ("Contract 6")

Tung Chung New Town Extension – Site Formation and Infrastructure Works at Tung Chung Valley, Phase 1

         Site Clearance

         Dust Emission

         Handling and storage of C&D materials generated from construction activities

         Noise from plant operation

         Emission of dark smoke from PMEs

         Tree Protection

         Good site practices

         Regular water spraying on stockpiles

         Provide tarpaulin sheets coverage on stockpiles

         Sorting and reuse of C&D materials as far as practicable

         Use of QPME and noise barrier/acoustic mat

         Regular maintenance of PMEs

         Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works

 


1.5        Summary of EM&A Requirements

The status of all environmental aspects is presented in Table 1.4. The EM&A requirements remained unchanged during the reporting period.

Table 1.4: Summary of Status for the Environmental Aspects under the Updated EM&A Manual  

Parameter

Status

Air Quality

 

Baseline Monitoring

The results of baseline air quality monitoring for TCW were reported in the Baseline Monitoring Report and submitted to EPD under EP Condition 3.4.

Impact Monitoring

To be commenced in December 2021 for TCW since no construction works carried out in Tung Chung Valley during the reporting period.

Noise

 

Baseline Monitoring (Construction Noise)

The results of baseline noise monitoring for TCW were reported in the Baseline Monitoring Report and submitted to EPD under EP Condition 3.4.

Impact Monitoring (Construction Noise)

Commenced on 3 November 2021 in Ma Wan Chung and ongoing. Monitoring conducted once per week. To be commenced in December 2021 in Tung Chung Valley since no constructions works carried out in Tung Chung Valley during the reporting period.

Impact Monitoring for Road Traffic Noise during Operational Phase

To be conducted during operational phase.

Fixed Noise Commissioning Test

To be implemented by the Contractor before operation of Tung Chung New Town Extension (TCNTE) development.

Water Quality

 

Baseline Monitoring

The results of baseline water quality monitoring for TCW were reported in the Baseline Monitoring Report and submitted to EPD under EP Condition 3.4.

Impact Monitoring

To be commenced in December 2021 for TCW since no construction works carried out in Tung Chung Valley during the reporting period.

Waste Management

 

Waste Monitoring

Ongoing.

Land Contamination

 

Contamination Assessment Plan (CAP), Remediation Action Plan (RAP) and Remediation Report (RR)

Proposed site investigation of the 4 no. potentially contaminated areas identified in the approved EIA Report is to be conducted after land resumption.

Ecology

 

Monitoring for Compensation Woodland

To be conducted when compensation woodland is planted.

Monitoring for Emergent Plant inside the future River Park

To be conducted when the emergent plants are planted.

Monitoring for Translocated Amphibians of Conservation Importance

Pre-construction survey was conducted during 20-22 October 2021. Capture and translocation exercise was conducted during 29-31 October 2021.

Monitoring for Preserved/Transplanted Plant Species of Conservation Importance

To be conducted after preservation/transplantation.

Baseline Monitoring for Tung Chung Stream Ecologically Important Stream (EIS) and Wong Lung Hang EIS

The results of baseline ecological monitoring for TCW were reported in the Baseline Monitoring Report and submitted to EPD under EP Condition 3.4.

Monitoring for Wong Lung Hang was not required and the proposal by the ET Leader of TCE was accepted by EPD on 2 September 2021.

Impact Monitoring for Tung Chung Stream Ecologically Important Stream (EIS) and Wong Lung Hang EIS

To be commenced in December 2021 for TCW since no construction works carried out in Tung Chung Valley during the reporting period.

Monitoring for Wong Lung Hang was not required and the proposal by the ET Leader of TCE was accepted by EPD on 2 September 2021.

Landscape and Visual

 

Baseline Monitoring

The results of baseline landscape and visual monitoring were reported in the Baseline Monitoring Report and submitted to EPD under EP Condition 3.4.

Site Environmental Audit

 

Regular Site Inspection

Commenced on 3 November 2021 for Ma Wan Chung and ongoing. Site Inspection for Tung Chung Valley will be commenced in December 2021 since no construction works carried out during the reporting period.

Plan on Provision of Buffer Zones implementation measures

To be implemented when the construction works in Tung Chung Valley commence in December 2021.

Plan for Review of Use of New Low Noise Road Surfacing Material implementation measures

Not applicable during this reporting period.

River Park Plan implementation measures

To be implemented when the construction works in Tung Chung Valley commence in December 2021.

Translocation Plan for Plant Species implementation measures

Under implementation by the Contractor of Contract 6.

Detailed Compensatory Woodland Planting Plan implementation measures

Not applicable during this reporting period.

Habitat Enhancement and Translocation Plan for Amphibian Species of Conservation Importance implementation measures

Under implementation by the Contractor of Contract 6.

Waste Management Plan implementation measures

Under implementation by the Contractors of Contracts 5 and 6.

Complaint Hotline and Email Channel

Under implementation by the Contractors of Contracts 5 and 6.

Environmental Log Book

Ongoing.

Taking into account the construction works, impact monitoring of noise and waste management were carried out in the reporting period. The monitoring schedule of noise monitoring is provided in Appendix F.

The EM&A programme also involved environmental site inspections and related auditing conducted by the ET for checking the implementation of the required environmental mitigation measures recommended in the approved EIA Report and relevant EP submissions, including Habitat Enhancement and Translocation Plan for Amphibian Species of Conservation Importance and Waste Management Plan.

1.6        Status of Statutory Environmental Compliance with the Environmental Permit

The status of statutory environmental compliance with the EP conditions under the EIAO, submission status under the EP and implementation status of mitigation measures are presented in Appendix D.

1.7        Status of Other Statutory Environmental Requirements

The environmental licences and permits (including Environmental Permit, waste disposal billing account, registration as chemical waste producer and construction noise permit) which were valid in the reporting period are presented in Appendix E. No non-compliance with environmental statutory requirements was recorded.

1.8        Reporting of EM&A Results

The EM&A programme for the Project required environmental monitoring for air quality, noise and water quality as well as environmental site inspections for air quality, noise, water quality, waste management, ecology, and landscape and visual impacts. The EM&A requirements and related findings for each component are summarised in the following sections:

     Section 2 -    Air Quality;

     Section 3 -    Noise;

     Section 4 -    Water Quality;

     Section 5 -    Ecology;

     Section 6 -    Waste Management Status;

     Section 7 -    EM&A Site Inspection;

     Section 8 -    Implementation Status of Environmental Mitigation Measures;

     Section 9 -    Summary of Exceedances of the Environmental Quality Performance Limit;

     Section 10 - Summary of Complaints, Notification of Summons and Successful Prosecutions;

     Section 11 - Future Key Issues; and

     Section 12 - Conclusions and Recommendations.

 

 

 

2        Air Quality

No impact air quality monitoring was scheduled in TCW during the reporting period since no construction works carried out in Tung Chung Valley. The impact air quality monitoring in TCW was scheduled to commence in December 2021.

 

 

3        Noise

3.1        Monitoring Requirements

According to the requirements in the Updated EM&A Manual, regular impact construction noise monitoring shall be carried out at the designated monitoring locations once per week during the construction period of the Project. Construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30min) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5min) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. As supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference. Since no construction works carried out in Tung Chung Valley during the reporting period, noise monitoring has been conducted in Ma Wan Chung only.

Further details of the impact construction noise monitoring are presented in the following sections.

3.2        Monitoring Locations

A total of five construction noise monitoring stations were identified for impact monitoring in the TCNTE possible development area (PDA) at Tung Chung West and are covered by this report.

Locations of the impact construction noise monitoring stations covered in this report are summarised in Table 3.1 and shown in Appendix F1.

Table 3.1: Impact Construction Noise Monitoring Stations

Monitoring Station

Location

Type of Measurement

NMS-CA-5

Village house in Ma Wan Chung (G/F)

Free field^

NMS-CA-6

Village house in Shek Mun Kap (G/F)

Free field^

NMS-CA-7

YMCA of Hong Kong Christian College (Roof Floor)

Façade

NMS-CA-8

Caritas Charles Vath College (Roof Floor)

Façade

NMS-CA-9*

Hong Chi Shiu Pong Morninghope School (Roof Floor)

Façade

Remark: * NMS-CA-9, which was described as “possible school development near Tung Chung Area 39” in the Updated EM&A Manual, was subsequently confirmed as “Hong Chi Shiu Pong Morninghope School” prior to commencement of baseline monitoring.

                ^  For Free Field measurement, +3dB(A) should be added to the measured results.

3.3        Monitoring Parameters, Frequency, Duration and Monitoring Dates

Table 3.2 summarises the parameters, frequency, duration and monitoring dates for impact construction noise quality monitoring during the reporting period.

Table 3.2: Impact Construction Noise Monitoring Parameters, Frequency, Duration and Monitoring Dates

Monitoring Station

Parameter

Frequency and Duration

Monitoring Dates

NMS-CA-5

30-min measurement between 0700 & 1900 hrs on normal weekdays (Monday to Saturday)

Leq, L10 and L90 would be recorded

Once every week during the construction of the Project

3, 9, 18 & 25 Nov 2021

NMS-CA-6

No monitoring was scheduled

NMS-CA-7

NMS-CA-8

NMS-CA-9

3.4        Action and Limit Levels

The Action and Limit Levels for construction noise of the Project are provided in Table 3.3 below.

Table 3.3: Action and Limit Levels for Construction Noise

Monitoring Station

Time Period

Action Level

Limit Level (dB(A), Leq(30min))

NMS-CA-5

NMS-CA-6

0700-1900 hrs on normal weekdays#

When one documented complaint is received

75

NMS-CA-7*

NMS-CA-8*

NMS-CA-9*

70

(65 during school examination periods)

Note:    # If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.

* Denotes school / educational institution.

3.5        Monitoring Equipment

Integrating Sound Level Meters were used to conduct impact construction noise monitoring. They were the Type 1 sound level meter capable of giving a continuous readout of the noise level readings including equivalent continuous sound pressure level (LAeq) and percentile sound pressure level (Lx). They complied with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1). Table 3.4 summarizes the equipment used in the impact construction noise monitoring. Copies of the calibration certificates for the sound level meters and acoustical calibrators are attached in Appendix F2.

Table 3.4: Noise Monitoring Equipment

Monitoring Station

Equipment & Model

 

Integrating Sound Level Meter

Acoustical Calibrator

NMS-CA-5

Rion NL-52 (serial no. 00331805)

Larson Davis CAL200 (serial no. 11333)

3.6        Monitoring Schedule for the Reporting Period

The schedule for impact construction noise monitoring during the reporting period is provided in Appendix F3.

3.7        Results and Observations

The monitoring results for construction noise are summarized in Table 3.5. The monitoring data and the graphical presentation are provided in Appendix F4.

Table 3.5: Summary of Construction Noise Monitoring Results in the Reporting Period

Monitoring Station

Average

(dB(A), Leq(30min))

Range

(dB(A), Leq(30min))

Limit Level

(dB(A), Leq(30min))

NMS-CA-5

57

54 – 60

75

The major noise sources during the construction noise monitoring in the reporting period included bird sound and aircraft as well as nearby construction sites.

No exceedance of Action and Limit Levels was recorded for construction noise monitoring in the reporting period. No action was thus required to be undertaken in accordance with the Event and Action Plan presented in Appendix F5.

 

 

4        Water Quality

No impact water quality monitoring was scheduled in TCW during the reporting period since no construction works carried out in Tung Chung Valley. The impact water quality monitoring in TCW was scheduled to commence in December 2021.

 

 

 

5        Ecology

No impact ecological monitoring was scheduled in TCW during the reporting period since no construction works carried out in Tung Chung Valley. The impact ecological monitoring in TCW was scheduled to commence in December 2021.

 

 

 

6        Waste Management Status

6.1        General

The Contractors of Contracts 5 and 6 have each obtained a waste disposal billing account and registered as chemical waste producer. Sufficient numbers of receptacles were available for general refuse collection and sorting.

All dump trucks engaged on site were equipped with Real Time Tracking and Monitoring (RTTM) system during the reporting period. The Surveillance Team of the ET conducted regular site inspections on the dump trucks and their track records. No illegal dumping and landfilling of C&D materials was found during the reporting period.

Wastes generated during this reporting period include mainly non-inert construction wastes. Reference has been made to the waste flow tables prepared by the Contractors. The quantities of different types of wastes and imported fill materials are summarised in Table 6.1.

 


Table 6.1: Quantities of Different Waste Generated and Imported Fill Materials 

Contract No.

Month / Year

Inert C&D Materials(a)

(in ‘000m3)

Imported Fill (public fill)(d)

(in ‘000m3)

Inert Construction Waste Re-used in the Contract

(in ‘000m3)

Inert Construction Waste Re-used in other Projects

(in ‘000m3)

Non-inert Construction Waste(b)

(in ‘000m3)

Recyclable Materials(c)

 (in ‘000kg)

Chemical Waste

(kg)

Contract 5

Nov 2021

0

0

0

1.43

0.049

0.17

0

Contract 6

Nov 2021

0

0

0

0

0.027

0

0

Notes:    (a) Inert construction and demolition wastes include hard rock and large broken concrete, and materials disposed as public fill.

(b) Non-inert construction wastes include general refuse disposed at landfill.

(c) Recyclable materials include metals, paper, cardboard, plastics and others.

(d) Imported fill materials include public fill.

          

 


7        EM&A Site Inspection

7.1        Monitoring Requirements

Environmental site inspections were carried out on a weekly basis with the Contractors and ER to monitor the implementation of proper environmental pollution control and mitigation measures for air quality, noise, water quality, waste management, ecology and landscape and visual impacts under the Project.

7.2        Site Inspections and Key Observations

In the reporting period:

     Five (5) site inspections were carried out on 4, 9, 16, 25 and 30 November 2021 for Contract 5; and

     No site inspections were carried out on in November 2021 for Contract 6.

Key observations during the site inspections are summarized in Table 7.1.

The Contractors have rectified all of the observations identified during environmental site inspections in the reporting period. The Contractors were reminded to implement all relevant mitigation measures related to construction dust, construction noise, water quality and waste management outlined in the EIA Report and EM&A Manual.


Table 7.1: Key Observations Identified during Site Inspections in this Reporting Period

Contract No.

Inspection Date(s)

Environmental Observation

Recommendation / Remark

Contract 5

4 Nov 2021

Area Part E in Ma Wan Chung

         No deficiency was observed

         Nil

9 Nov 2021

Area Part E in Ma Wan Chung

         No deficiency was observed

         Nil

16 Nov 2021

Area Part E in Ma Wan Chung

         No deficiency was observed

         Nil

25 Nov 2021

Area Part E in Ma Wan Chung

       No deficiency was observed

        Nil

30 Nov 2021

Area Part E in Ma Wan Chung

      No deficiency was observed

        Nil

 


8        Implementation Status of Environmental Mitigation Measures

A summary of the Environmental Mitigation Implementation Schedule is presented in Appendix C. The necessary mitigation measures were implemented properly for the Project.

 

 

9        Summary of Exceedances of the Environmental Quality Performance Limit

No impact air quality monitoring was scheduled during the reporting period.

The monitoring results for construction noise monitoring complied with the Action/Limit Levels in the reporting period.

No impact water quality monitoring was scheduled during the reporting period.

No impact ecological monitoring was scheduled during the reporting period.

 

 

10   Summary of Complaints, Notification of Summons and Successful Prosecutions

There was no environmental complaint, notification of summons or prosecution recorded in the reporting period.

Statistics on complaints, notifications of summons, successful prosecutions are summarised in Appendix G.

 

 

11   Future Key Issues

11.1     Construction Programme for the Coming Reporting Period

Works to be undertaken in the next monitoring period of December 2021 are summarized in Table 11.1 below, together with the key issues and the key mitigation measures.

The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures. The ET will also recommend to the Contractors about the environmental toolbox topics on the abovementioned key issues for the next reporting period.

11.2     Monitoring Schedule for the Coming Reporting Period

The tentative schedules for environmental monitoring in December 2021 are provided in Appendix H.


 Table 11.1: Major Activities for the next Reporting Period

Activities

Key Issues

Key Mitigation Measures

Contract No. NL/2020/05 ("Contract 5")

Tung Chung New Town Extension – Site Formation and Infrastructure Works at Ma Wan Chung

         Ground Investigation

         Geotechnical Investigation

         Site Survey

         Dust Emission

         Handling and storage of C&D materials generated from construction activities

         Noise from plant operation

         Emission of dark smoke from PMEs

         Tree Protection

         Good site practices

         Regular water spraying on stockpiles

         Provide tarpaulin sheets coverage on stockpiles

         Sorting and reuse of C&D materials as far as practicable

         Use of QPME and noise barrier/acoustic mat

         Regular maintenance of PMEs

         Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works

Contract No. NL/2020/06 ("Contract 6")

Tung Chung New Town Extension – Site Formation and Infrastructure Works at Tung Chung Valley, Phase 1

         Site Clearance

         Fence Wall Construction

         Dust Emission

         Handling and storage of C&D materials generated from construction activities

         Noise from plant operation

         Emission of dark smoke from PMEs

         Tree Protection

         Good site practices

         Regular water spraying on stockpiles

         Provide tarpaulin sheets coverage on stockpiles

         Sorting and reuse of C&D materials as far as practicable

         Use of QPME and noise barrier/acoustic mat

         Regular maintenance of PMEs

         Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works

 


12   Conclusions and Recommendations

General

This EM&A Report presents the findings of the EM&A activities undertaken for the Project – i.e., Tung Chung New Town Extension (TCNTE) development in Tung Chung West (TCW) – during the period from 3 to 30 November 2021 in accordance with the Updated EM&A Manual and the requirements of the Environmental Permit (EP) (No. EP-519/2016).

The construction works for the Project commenced on 3 November 2021. The commencement date of the construction works at Tung Chung Valley will be 30 November 2021.

Air Quality

No impact air quality monitoring was scheduled during the reporting period.

Noise

Impact noise monitoring at the village house in Ma Wan Chung (NMS-CA-5) was carried out during the reporting period, and the monitoring results complied with the corresponding Action/Limit Levels. 

Water Quality

No impact water quality monitoring was scheduled during the reporting period.

Ecology

No impact ecological monitoring was scheduled during the reporting period.

Environmental Site Inspections

Environmental site inspections were carried out for Contract 5 only during the reporting period. No deficiency was observed during the reporting period.

Environmental Complaint, Notification of Summons or Prosecution

There was no environmental complaint, notification of summons or prosecution recorded in the reporting period.

Recommendations

The ET will keep track of the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.

 

 

Figures

Map

Description automatically generated

Map

Description automatically generated

 

 

Appendices

A.      Project Organisation

B.      Construction Works Programme

C.      Environmental Mitigation Implementation Schedule

D.      Status of Submissions and Implementation Status of Mitigation Measures under EP

E.      Status of Statutory Environmental Requirements

F.       Noise

F1.  Locations of Construction Noise Monitoring Stations

F2.  Construction Noise Monitoring Equipment Calibration Certificates

F3.  Construction Noise Monitoring Schedule

F4.  Construction Noise Monitoring Results

F5.  Construction Noise Monitoring Event and Action Plan

G.      Cumulative Statistics on Exceedances, Environmental Complaints, Notifications of Summons and Status of Prosecutions

H.      Monitoring Schedule for the Next Reporting Period